REBORN DANUBE - STEP BY STEP
Post
Published 29. Aug 2023 by Michaela_Kalivodova in
Another step to restoration of Danube inland delta
Restoration work on the lower Vojčianske branch has started

A few days ago we started the restoration works on the lower Vojčianske branch. Yesterday we came to document it. 🚜💧

We are dredging and restoring its lower part and changing the pipe culverts under the forest road to frame culverts. These procedures are more suitable for fish and for restoring the maximum possible river dynamics left in the altered Inland Danube Delta after the construction of the Gabčíkovo hydroelectric power plant.

We are looking forward to the result, at the moment it looks in progress and muddy.

We are restoring the lower section of the Vojčianske arm from the #LIFE_DunajskeLuhy project, together with WWF Slovakia, VODOHOSPODÁRSKA VÝSTAVBA, ŠTÁTNY PODNIK and last but not least with the NAUTILUS excavators.